Genetic testing startup: a Project Management Office (PMO) for 30+ projects

PPS Consulting India set up a Project Management Office (PMO) from scratch for a venture-backed genetic testing startup in the US, bringing 30+ projects and five project managers onto one plan and one weekly cadence. Leadership and the investors got one view of what was on track, what was at risk and why, and which decisions were waiting on them.

At a glance

30+ projects, one plan

five project managers on one weekly cadence, and one view for leadership and investors

Client
A venture-backed genetic testing startup
Sector
Healthcare services
Where
United States
The work
Transformation PMO
Scale
30+ projects, five project managers
Led by
Rahul Kulkarni and Rashmi Kulkarni

What was the problem?

The startup was running more projects than it could see. There was no central project management and no agreed way to prioritise, so leadership struggled to see which initiatives were moving and to work across functions.

As a genetic testing business it also carried compliance risk under HIPAA, the US health privacy law, and medical regulations.

What did we do?

  1. Design

    A prioritisation framework for deciding which projects go ahead, a governance framework with escalation rules, and one plan template with the same milestones for every project.

  2. Build

    The PMO itself: five project managers on a shared plan, status in red, amber or green with a written reason, risks and dependencies in one register, a decision log with owner and date, and every change request routed through the PMO. Compliance tracking for HIPAA and medical regulations sat in the same system.

  3. Adopt

    A weekly rhythm: a 20-minute stand-up with all five project managers on Monday, dependencies and risks midweek, a one-page leadership status on Friday, and a monthly re-plan against capacity. A reporting model for the leadership team and the investors: milestones due in the next 30 days, projects at risk and why, and decisions waiting on leadership.

The method, phase by phase

What did we build?

Genetic testing startup: plan on a page Illustrative schematic, not a client document

Five example projects, one plan

  • Lab automation
    1. Design and build
    2. Validate
    Handover
  • Laboratory information system
    1. Configure and migrate
    2. Train
    Live
  • Assay validation
    1. Validation runs
    Sign-off
  • Clinical partner onboarding
    1. Contracts
    2. Onboard partners
  • Reporting portal
    1. Build
    2. Pilot
    Pilot done

Each project has a named project manager, the same plan template and the same milestones.

One method

  • Shared plan template, same milestones
  • Status in red, amber or green, with a written reason
  • Risks and dependencies in one register
  • Decision log, with owner and date
  • Change requests through the PMO

Cadence

Mon
Stand-up, five project managers, 20 minutes
Wed
Dependencies and risks
Fri
Leadership status, one page
Monthly
Re-plan against capacity

Leadership view

  • Milestones due in the next 30 days
  • Projects at risk, and why
  • Decisions waiting on leadership

What changed?

  • A working PMO, set up from nothing.
  • 30+ projects tracked and managed on one plan.
  • Leadership and investors seeing the same weekly view, including the decisions waiting on them.
  • Stronger collaboration across the leadership team.
  • Compliance risks tracked and escalated through the same governance as every other project.

Is this relevant to you?

It is if:

  • You have more initiatives running than anyone can list from memory.
  • Your investors or board ask for status, and the answer takes a week to put together.
  • You work under regulation, and compliance tasks compete with everything else.

Where would we start with you?

With the PPS Backbone Review: four weeks, a fixed fee of ₹1,50,000 to ₹3,50,000 plus GST and expenses, one fix working by the end, and a plan with owners and measures that is yours to keep, whether or not we build it with you.

How the Review works

9 workstreams, one cadence

nine project managers reporting in one format, with a one-page status for the CFO every week

Global finance transformation: nine workstreams on one plan

Relevant if you are running several initiatives at once and each one reports differently.

Professional and business services · Global

All results

  • 100+ engagements
  • 62,000+ delivery hours
  • Top 1% Expert-Vetted on Upwork
  • 100% job success, independently verified

Across Upwork and direct contracts, including the people on our project teams.

  • MIT MicroMasters, Supply Chain
  • Six Sigma Black Belt
  • PRINCE2 Practitioner

Questions about this case

Does a startup need a PMO?

Once it runs more projects than its leaders can track in their heads, yes. This one was five project managers on one plan template and a short weekly rhythm.

How do you handle HIPAA and medical compliance in a PMO?

As tracked work, like everything else: compliance tasks sit in the same plan and register, with owners and escalation rules, so they come up in the weekly review.

By Rahul Kulkarni, MIT MicroMasters (Supply Chain) · Last updated

Tell us two things.

What you're trying to achieve in the next 90 days, and what's breaking in execution. We'll tell you plainly what we'd fix first.

Book a discovery call

Free, no obligation, and under an NDA if you prefer.

Or write to consult@ppsconsulting.biz WhatsApp +91 93246 21840 (opens in a new tab)